(A) The minimum size for new water and/or sewer mains is established by the village as six inches in diameter.
(B) The size (diameter) of the proposed waterline and/or sewerline shall be approved by the Village Water and Sewer Department Superintendent. If it is determined that the village requires a waterline and/or sewerline larger in diameter than needed by the proposed development, the difference in the cost of materials will be paid by the village to the property owner/developer; provided:
(1) The property owner/developer request said reimbursement;
(2) The request for said reimbursement is approved by Village Council and the Water and Sewer Department Superintendent;
(3) The actual difference in material costs is clearly documented and the request for payment is submitted in a timely manner (no more than six months after acceptance of the waterline and/or sewerline by the village); and
(4) Reimbursement under the rotary fee policy will be based upon the project cost exclusive of over-sizing costs.
(Ord. 863, passed 10-7-2019)