§ 152.202 DRAINAGE SYSTEM DESIGN AND EVALUATION.
   (A)   (1)   The following criteria should be used in evaluating and designing the drainage system. The design will provide capacity to pass the ten-year, 24-hour peak flow in the minor drainage system and an overload flow path (major drainage system) for flows in excess of the design capacity.
      (2)   Whenever practicable, the stormwater systems shall not result in the inter-basin transfer of drainage unless no other alternative exists.
   (B)   The design rainfall recurrence interval shall be set by the design application as follows:
 
Bridges
100-year
Detention
100-year
Emergency overflow routing
100-year
Roadway underpasses
50-year
Storm sewers
10-year
Swales, ditches, and culverts
25-year
 
(Ord. passed - -)