§ 154.591 SITE PLAN REVIEW.
   (A)   An application for a building or parking lot permit shall promptly be forwarded to the appropriate officials.
   (B)   Review must be completed within 15 days of the receipt by the county of a complete site plan review application. If, in the judgment of the appropriate officials, the site plan review application does not contain sufficient information to enable the appropriate county officials to properly carry out its responsibilities, the appropriate officials may request additional information from the applicant. In that event, the 15-day period previously referred to shall be suspended, pending the receipt of all information requested by the appropriate officials.
(Ord. passed 5-16-2023)