§ 153.330 PROCESS AND TIMING.
   (A)   Approval process. An ADU or JADU is considered and approved ministerially, without discretionary review or hearing, if it meets the minimum standards in this chapter.
   (B)   Timing. The city must act on an application to create an ADU or JADU within 60 days from the date that the city receives a completed application, unless either:
      (1)   The applicant requests a delay, in which case the 60-day time period is tolled for the period of the requested delay; or
      (2)   In the case of a JADU and the application to create a JADU is submitted with a permit application to create a new single-family dwelling on a lot, the city may delay acting on the permit application for the JADU until the city acts on the permit application to create a new single-family dwelling, but the application to create a JADU will still be considered ministerially without discretionary review or a hearing.
(Ord. 2021-007, passed 12-14-21)