§ 113.048 SYSTEM CONSTRUCTION SCHEDULE.
   (A)   Grantee shall comply with the requirements of the cable system construction schedule, if any, contained in the franchise agreement and any amendments thereto.
   (B)   Construction of the cable system and service need not be provided where power and telephone utility services are not available.
   (C)   In the franchise agreement, grantee shall provide a detailed construction plan indicating progress schedule, area construction maps, test plan, and dates for offering service. In addition, as long as construction has not been completed, grantee shall provide grantor an update of this information for grantor on a monthly basis, showing specifically whether schedules are being met and the reasons for any delay.
   (D)   Failure to begin construction within six months after award of the franchise shall be grounds for immediate franchise termination, at the option of grantor.
(Ord. 94-09, passed 9-12-94)