§ 55.27 TAP FEE.
   (A)   Sewer Tap.
      (1)   Cost         $250
      (2)   Sewer Tap fee includes plans review and construction inspection. All materials and work, including installation of sewer main tap saddle, installation of lateral and restoration of excavation including paving is supplied and performed by the contractor.
   (B)   Water Tap.
      3/4" Water Service Line   $650
      1" Water Service Line   $1,150
      Greater than 1"      $250
   (C)   For 3/4-inch and 1-inch Water Taps Only. Rising Sun Municipal Utility provides materials and labor to install the water main tap, water service line to the meter box, meter box, meter setting and water meter. Meter box is placed at edge of property in an accessible location.
   (D)   For Water Taps greater than one inch. Water Tap fee includes plans review and construction inspection. All materials and work, including installation of water main tap, water service line to the meter box, meter box, meter setting, water meter and restoration of excavation including paving is paid for by the owner requesting the service. Meter box is placed at a location approved by the Rising Sun Municipal Utility.
(Ord. 1997-6, passed 12-4-97)