§ 156.645 CONSTRUCTION OF CELLULAR/WIRELESS/PERSONAL COMMUNICATION FACILITIES AND TOWERS.
   (A)   Construction of all towers must begin within 90 days after issuance of a permit. Once construction begins, all towers must be completed within 90 days.
   (B)   Any permit issued prior to the adoptive date of this amended ordinance must have construction started within 180 days from the date of the adoption. If construction does not begin within 180 days of issuance, then such permit shall be void.
   (C)   All tower placements must be pursuant to the amended provisions of this chapter thereafter.
   (D)   Within 30 days following erection of the Tower, the applicant/permit holder shall submit two sets of "as-built" plans to the Executive Director of the Area Plan Commission, certified by the professional engineer who designed the tower, confirming that the tower has been built/constructed to the specifications and the design contained within the plans submitted with the application.
(Ord. passed - -2006, § 80.49(F); Ord. 2019-02, passed 4-22-2019) Penalty, see § 156.999