§ 59.059 INSPECTION.
   (A)   The applicant for the building sewer shall notify the Director at least one working day in advance of the date the building sewer will be ready for inspection and connection to the public sewer. The connection shall be made under the supervision of the Director or his or her representative.
   (B)   The applicant shall be required to perform and pass a low pressure air test on all newly installed laterals. The applicant shall be required to perform and pass a mandrel test on all newly installed sewers. The applicant shall also perform and pass a vacuum test on all newly installed manholes. These tests or others required by the District shall meet the standards and requirements of the City Sanitary District.
   (C)   Any tap not made in accordance with the foregoing provisions shall be deemed an illegal installation and, upon discovery, shall be promptly disconnected at the expense of the property owner and shall remain disconnected until all provisions of this section have been complied with.
(Prior Code, § 50.35)