§ 155.39 PROCEDURES FOR ISSUANCE OF CERTIFICATE BY BUILDING INSPECTOR.
   (A)   The applicant shall file sufficient information as to accurately depict the location, design and scope of the work to be done.
   (B)   The staff shall review the information and promptly notify the applicant if the material is not adequate for review and advise the applicant what specific information will be required. The staff shall review the application for compliance with the adopted guidelines and consult with other divisions as appropriate to ensure proper review.
   (C)   Upon determination that all requirements of the guidelines have been met, and that the application complies with the requirements of the Board, the Building Inspector shall approve the application and issue the Certificate of Appropriateness.
   (D)   If any question arises as to compliance or if the Building Inspector or applicant feels that the application raises issues deserving review by the full Board, the request shall be referred to the Board for action.
   (E)   Upon approval by the Building Inspector, the staff shall issue the Certificate of Appropriateness and notify the applicant. In addition, the staff shall forward a copy of the certificate and application materials to the Building Inspector.
(Ord. 04-02, passed 2-3-04)