1101.03 PLOT PLAN APPROVAL.
   (a)   Council hereby establishes the requirement of submitting plot plans for the proposed construction or development of any parcel or lot to the Planning and Zoning Commission. Once the plans are submitted to the Commission, if applicable, they shall be submitted to the Engineer, Building Inspector, Storm Water Committee and City Solicitor for comments.
   (b)   The Planning and Zoning Commission after receiving all necessary reports shall then examine the plot plan and render a decision within ten days.
   (c)   The Planning and Zoning Commission after rendering its decision shall forward its recommendations to Council who shall then act on the recommendation within thirty days.
   (d)   The plot plan shall specifically set forth building sites, drainage, water supply, paved streets, drives, parking, open areas, zoning density, utility lines and connections and any additional data that may be requested by the Planning and Zoning Commission, City Engineer, Building Inspector, Storm Water Committee or Council.
   (e)   The applicant submitting the plot plan for the proposed construction or development of any parcel or lot shall be required to pay a fee for examination of the plot plan by the City Engineer. The fee shall be paid on or before the issuance of either a zoning certificate or building permit by the City.
(Ord. 5-2004. Passed 7-13-04.)