(A) Pre-application conference(s) are held with the Zoning Administrator and Planning Commission to obtain information and guidance in preparing the application.
(B) Applications for the mobile home park are submitted with the site plans and descriptive statement to the City Manager.
(C) The City Manager shall distribute copies to the Planning Commission for review.
(D) A public hearing on the application and site plan before the Planning Commission is scheduled and held.
(E) The Planning Commission shall, following the public hearing, either approve the application as submitted, approved with conditions, or deny the application, specifying the reasons for denial.
(F) If approved, construction of the Mobile Home Park shall commence within one year following approval by the Department of Commerce.
(Ord., § 413, passed 6-11-2002)