(A) As an initial step in applying for the issuance of a building permit for the construction, alteration, or expansion of any structure in any zone excluding the R-15, R-12, and R-10 Zones, a site plan shall be submitted which shall include the following: grading; engineering design; construction size, height, shape and location of building; location and design of parking areas; pedestrian and vehicular circulation on site; and plans for collecting and depositing storm water and natural or artificial water courses.
(B) (1) The site plan must be approved by the Public Works Director of the town and by the Inspections Superintendent before a building permit is issued; however, if the site plan is disapproved, the applicant may appeal such decision to the Planning and Zoning Commission and then to the Board.
(2) The structure must be constructed, altered, or expanded in accordance with the site plan before a certificate of occupancy is issued by the Inspections Superintendent.
(Prior Code, § 9-4013) (Ord. passed 4-27-1970)