§ 51.172 NEW SOURCE AND NEW USER.
   At least 90 days prior to the anticipated start-up, any new source, which is a source that becomes a user subsequent to the proposal of an applicable categorical pretreatment standard that is later promulgated, and any new user considered by the city to fit the definition of SIU shall apply for a wastewater discharge permit and will be required to submit to the city at least the information listed in divisions (A) through (E) of § 51.174. A new source or new user cannot discharge without first receiving a wastewater discharge permit from the city. New sources and new users shall also be required to include in their application information on the method of pretreatment they intend to use to meet applicable pretreatment standards. New sources and new users shall give estimates of the information requested in § 51.174 (D) and (E).
(Ord. 9399, passed 2-24-2020)