§ 154.041 FAILURE TO PROCEED.
   The subdivider shall complete off-site improvements within one year from the date of the final plat recording. Upon written application of the subdivider the Public Works Director may consider a request for a one year extension to complete improvements. In the event the Public Works Director denies the subdivider's request for extension, the subdivider may appeal within 30 days of denial to the Town Council. If subdivider fails to complete construction of off-site improvements within one year, or within two years if an extension is granted, the town may complete the construction of such off-site improvements by drawing upon the funds posted by the subdivider for assurance.
(Ord. 21-11, passed 10-26-2021)