§ 51.36 REIMBURSEMENT CHARGE.
   (A)   A public sewer reimbursement charge will be based on either one-half the cost per lineal foot of the sewer main extension abutting the premises of the part desiring to obtain a connection or connections to the main, or by an agreed upon fee per acre for the area served by the connection.
   (B)   A certified cost per lineal foot of the sewer main extension shall be obtained by taking the total cost of construction of the extension divided by the total lineal feet of the sewer main extension installed.
   (C)   The per parcel cost for reimbursement shall be obtained by one of the following methods, as appropriate:
      (1)   Dividing the total cost of construction of the sewer main extension by the total number of parcels to be served by the extension and subtracting the number of parcels to be served in the applicant’s development; or
      (2)   Determining the difference between the total cost of construction of the sewer main extension and the cost for constructing an extension adequate to serve only the area of the applicant’s development and dividing the difference by the number of parcels served in addition to the applicant’s development.
(Prior Code, § 16-1-6) (Ord. 91-02, passed - -1991; Ord. 91-04, passed - -1991; Res. 91-09, passed - -1991; Ord. 92-04, passed - -1992; Res. 92-04, passed - -1992; Res. 94-22, passed - -1994; Ord. 00-04, passed - -2000; Ord. 10-01, passed - -2010)