(a) Compliance with Regulations Determinations.
(1) The Building Officer shall examine applications for building permits.
(2) Within fourteen (14) calendar days of receipt of the building permit application, the Building Officer shall send an email notification or post-mark a letter to the applicant, notifying the applicant that:
A. The building permit application is incomplete and requires additional application materials;
B. The building permit application is complete but is denied and indicating the rationale for such determination and optionally recommending that the applicant seeks a variance or other remedy;
C. The building permit application is complete, and the proposed project complies with the regulations of the Zoning Code, and a building permit is granted;
D. The building permit application is complete, and the proposed project nearly complies with regulations of the Zoning Code and, with a de minimis variance, fully complies with the regulations of the Zoning Code, and a building permit is granted;
E. The building permit application is complete, and the proposed project requires a variance or conditional use approval and may be forwarded to the Board of Zoning Appeals for review; or
F. The building permit application is complete, but the project requires a zoning text or map amendment and may be forwarded to the Commission for review.
(3) If a building permit application is denied due to being incomplete or noncompliant with a regulation of the Zoning Code, the applicant may re-submit the building permit application with modifications to the Building Officer. If the applicant re-submits the building permit application within fourteen (14) calendar days of receipt of notification of denial, no application submission fee payment will be required in excess of the initial application submission fee, except if the type of application is modified. If the applicant does not resubmit a complete application within fourteen (14) calendar days of notification by the Building Officer, the building permit application will not be processed, and the permit application fee will be surrendered to the City.
(Ord. 2022-110. Passed 12-12-22.)