All infill development applications shall include documentation, provided by the applicant, demonstrating that the proposal complies with the following criteria:
A. Bound on two (2) or more sides by existing development;
B. Where the utilities are available in abutting streets and/or alleyways so that extension of trunk utility lines is not required;
C. The project has an elevation less than or equal to 4,600';
D. The project is either not platted or has been platted for a minimum of twenty-five (25) years in its current configuration from the date of application submittal; and
E. The project is no larger than three (3) acres. (Ord. 3115 § 5, 2023: Ord. 3075, 2021: Ord. 2846 § 1, 2008)