A. A type 1 WCF permit shall be required for an "eligible facilities request" which includes:
1. Collocation of new transmission equipment;
2. The removal of transmission equipment;
3. The replacement or modification of transmission equipment;
4. Distributed antenna system and small cells.
B. A type 2 WCF permit shall be required for:
1. Any modification of an eligible support structure, including the collocation of new equipment, that substantially changes the physical dimensions of the eligible support structure on which it is mounted; or
2. Any collocation not eligible for a type 1 permit; or
3. Any roof mounted antenna and support system for an antenna not exceeding ten feet (10') above the highest portion of the roof; or
4. A new tower located in the public right-of-way.
C. A type 3 WCF permit shall be required for siting of any new WCF tower that is not a collocation subject to a type 1 or 2 WCF permit as outlined in this section. (Ord. 3025, 2019: Ord. 2979, 2016)