8.48.100: MONITORING OF DISCHARGES:
   A.   Applicability: This section applies to all facilities that have stormwater discharges associated with commercial activity and industrial activity, including construction activity.
   B.   Access To Facilities:
      1.   The director of public works or his authorized representative shall be permitted to enter and inspect facilities subject to regulation under this chapter as often as may be necessary to determine compliance with this chapter. If a discharger has security measures in force which require proper identification and clearance before entry into its premises, the discharger shall make the necessary arrangements to allow access to the director of public works or his authorized representative.
      2.   Facility operators shall allow the director of public works or his authorized representative ready access to all parts of the premises for the purposes of inspection, sampling, examination and copying of records that must be kept under the conditions of an NPDES permit to discharge stormwater, and the performance of any additional duties as defined by state and federal law related to said discharges.
      3.   The director of public works shall have the right to set up on any permitted facility such devices as are necessary in the opinion of the authorized enforcement agency to conduct monitoring and/or sampling of the facility's stormwater discharge.
      4.   The director of public works has the right to require the discharger to install monitoring equipment as necessary. The facility's sampling and monitoring equipment shall be maintained at all times in a safe and proper operating condition by the discharger at its own expense. All devices used to measure stormwater flow and quality shall be calibrated as required by the manufacturer's operation manual to ensure their accuracy.
      5.   Any temporary or permanent obstruction to safe and easy access to the facility to be inspected and/or sampled shall be promptly removed by the operator at the written or oral request of the director of public works and shall not be replaced. The costs of clearing such access shall be borne by the operator.
      6.   Unreasonable delays in allowing the director of public works access to a permitted facility is a violation of a stormwater discharge permit and of this chapter. A person who is the operator of a facility with an NPDES permit to discharge stormwater associated with industrial activity commits a misdemeanor offense if the person denies the director of public works access to the permitted facility for the purpose of conducting any activity authorized or required by this chapter.
      7.   If the director of public works has been refused access to any part of the premises from which stormwater is discharged, and he/she is able to demonstrate probable cause to believe that there may be a violation of this chapter, or that there is a need to inspect and/or sample as part of a routine inspection and sampling program designed to verify compliance with this chapter or any order issued hereunder, or to protect the overall public health, safety, and welfare of the community, then the director of public works may seek issuance of a search warrant from any court of competent jurisdiction. (Ord. 2860, 2008)