(A) The project owner/developer shall secure the services of an independent testing laboratory for the quality control testing for all backfill and earth work compaction density control and all sampling and testing of concrete, asphalt and aggregate.
(B) Before a certificate of occupancy (temporary or final) is issued for a project, owner/developer of the property must submit certified copies of all test results, plus a certification from a registered civil engineer certifying the following.
(1) All subgrades have proper compaction and have been established at proper design grade.
(2) All utilities within the road proper and/or within close proximity of the pavement area have been compacted to the specifications set forth by the project designer and also in accordance with township standards.
(3) All aggregate base courses are of specified materials, depth and compaction.
(4) All asphalt base courses have been installed at proper temperature, thickness and compaction.
(5) All asphalt surface courses have been applied at proper temperature, thickness and compaction.
(6) All concrete paving areas have been installed to proper thickness and all standard tests, such as slump and strength tests, have been run and are acceptable.
(7) All control joints and expansion joints, necessary and required, have been properly installed.
(Prior Code, § XII-4.03)