921.19 ICR SYSTEM IMPLEMENTATION.
   (a)   The ICR period shall commence upon the completion of Step 3 construction, final inspection and the subsequent beneficial use of the wastewater treatment works. The date of commencement for the ICR period shall be the date of beneficial use of the wastewater treatment works by the first user, regardless of whether or not the first user is an industrial user.
   (b)   Within thirty (30) days after the commencement of the ICR period, the Municipality shall establish the accounting period for the ICR system. The Municipality shall notify the U.S. EPA Regional Administrator, in writing, within sixty (60) days after the commencement of the ICR period, of the date of the implementation of the ICR system and of the ICR accounting period.
   (c)   Industrial users shall be required to make the first ICR payment to the Municipality no later than twelve (12) months after the commencement of the ICR period.
(Ord. 18-1980. Passed 10-13-80.)