§ 91.013 CARE AND CLEAN UP OF EXCAVATED MATERIAL.
   (A)   Care of excavated material.
      (1)   All material excavated from trenches and piled adjacent to the trench or in any street shall be piled and maintained in such manner as not to endanger those working in the trench, pedestrians, or users of the streets and so that as little inconvenience a possible is caused to those using streets and adjoining property. Where the confines of the area being excavated are too narrow to permit the piling of excavated material beside the trench, such as might be the case in a narrow alley, the Superintendent of Public Works shall have the authority to require that the permittee haul the excavate material to a storage site and then rehaul it to the trench site at the time of backfilling. It shall be the permittee’s responsibility to secure the necessary arrangements for all required storage and disposal sites.
      (2)   All material excavated shall be laid compactly along the side of the trench and kept trimmed so as to cause as little inconvenience as reasonably possible to vehicular and pedestrian traffic, or as specified by the Superintendent of Public Works. Whenever necessary, in order to expedite the flow of traffic or to abate the dirt or dust nuisance, toe boards or bins may be required by the Superintendent of Public Works to prevent the spreading of dirt into traffic lanes.
   (B)   Clean up. As the excavation work progresses, all streets shall be thoroughly cleaned of all rubbish, excess earth, rock, and other debris resulting from such work. All clean up operations at the location of such excavation shall be accomplished at the expense of the permittee and shall be completed to the satisfaction of the Superintendent of Public Works. In any event immediately after completion of said work, the permittee shall, at his or her own expense, clean up and remove all refuse and unused materials of any kind resulting from said work, and upon failure to do so within 24 hours after having been notified to do so by the Superintendent of Public Works, said work may be done by the Superintendent of Public Works and the cost thereof charged to the permittee, and the permittee shall also be liable for the cost thereof under the surety bond provided hereunder.
(1995 Code, § 91.13) (Ord. 0007, passed 5-3-1982) Penalty, see § 91.999