(A) Sections 152.355 through 152.357 set the standards that shall apply under normal soils conditions. However, where soils are unusually good or unusually unstable, the Public Works Director may allow or require the developer to have soil tests run and a pavement design made by a qualified soils engineer.
(B) Under these circumstances, the Public Works Director may allow pavement sections constructed to lesser standards than those set forth above (for good soils) or require pavement sections constructed to greater standards than those set forth above (for unstable soils).
(Ord. passed 12-20-2001) Penalty, see § 152.999