(A) A permit shall be applied for and issued by the Zoning Administrator before construction shall begin on any swimming pool. The application for the permit shall be accompanied by a complete and detailed set of plans and specifications of the swimming pool.
(B) Before any permit shall be issued, such plans and specifications shall be approved by the Building Inspector and the county’s Health Department, and before any swimming pool shall be used, a final inspection and approval shall be required from both the Building Inspector and the county’s Health Department.
(Prior Code, § 4-32) Penalty, see § 150.99
Cross-reference:
Filling and draining swimming pools, see § 50.06
Swimming pool construction requirements, see § 150.27
Swimming pool construction, use, and inspections, see § 91.60