§ 151.094 FINAL APPROVAL.
   (A)   Once preliminary approval has been granted by the Plan Commission, final approval may be granted by a hearing committee consisting of the following members provided no changes have been made that were not approved by the Commission.
      (1)   President of the Plan Commission.
      (2)   Zoning Administrator.
      (3)   County Surveyor.
      (4)   Two members of the Plan Commission other than the President.
      (5)   One member of the Common Council.
   (B)   Preliminary approval by the Commission expires upon the expiration of a three-year period immediately following that approval, unless all parts of the phase have been platted and recorded.
   (C)   Three copies of final approval plan shall be submitted to the Commission on 24 by 30, 5 mils, single mat mylar print.
   (D)   The planned unit development may be submitted in phases; however, the Plat Committee must approve each phase.
   (E)   An appeal of the decision of the Plat Committee shall be to the Commission.
   (F)   Should changes be made from preliminary approval t the final approval, a public hearing shall be required for secondary approval.
   (G)   After final approval has been granted all plans shall be recorded with the Recorder and no changes may be made without the approval of the Commission.
(Ord. 5-2002, passed 3-4-02) Penalty, see § 151.999