9-2-2: PERMIT FEES:
   A.   Building Permit Fees:
Valuation
Permit Fee
Valuation
Permit Fee
$0.00 to $140.00
$ 0.00
$140.01 to $5,000.00
25.00
$5,000.01 to $7,500.00
28.00
$7,500.01 to $10,000.00
31.00
$10,000.01 to $15,000.00
34.00
$15,000.01 to $20,000.00
38.00
$20,000.01 to $50,000.00
$38.00 plus $2.50 per $1,000.00 over $20,000.00
$50,000.01 to $75,000.00
$131.00 plus $2.00 per $1,000.00 over $50,000.00
$75,000.01 to $100,000.00
$194.00 plus $1.50 per $1,000.00 over $75,000.00
$100,000.01 to $500,000.00
$241.00 plus $1.00 per $1,000.00 over $100,000.00
$500,000.01 and up
$740.00 plus $0.75 per $1,000.00 over $500,000.00
Additional fees are as follows:
 
Sign permits
$31.00
Fence permits
25.00
Demolition permits
25.00
Certificate of occupancy
6.00
 
(Ord. 2005-1249, 11-15-2005)
   B.   Residential Fees:
      1.   Electrical Fees: The electrical inspector shall charge for residential electrical permits and services the amounts provided in the following schedule: (Ord. 2005-1249, 11-15-2005; amd. 2016 Code)
Service
Fee
Service
Fee
Residential electrical permit
$10.00
Residential inspections:
 
 
Single-family dwellings:
 
 
Up to 20 amp service
41.00
 
200 to 400 amp service
50.00
 
Each additional 100 amps
over 400 amps
13.00
 
Apartment buildings
The same fees shall apply for the same size service as stated above
Residential room additions without service change
$29.00
Pools and garages
23.00
Temporary service included in building fee
 
Furnaces and air conditioners up to 4 tons
13.00
Air conditioners more than 4 tons
23.00
Dwelling owner inspections
94.00
Temporary pole service (if permit is for temporary service only)
25.00
 
      2.   Notice Of Changes After Inspection; Reinspections:
         a.   After inspection, the inspections department shall leave the owner or tenant a written notice of any changes or alterations as may be required, and such changes or alterations shall be made within thirty (30) days after receipt of such written notice unless, in the opinion of the inspector, such changes should be made at once, and the inspections department shall reinspect such changes as given in the written notice. A fee shall be charged for this service according to the fees listed herein.
         b.   For each reinspection for noncompliance to the building/electrical code or premature inspection request, the following will be charged:
 
First reinspection or premature inspection request
Free
Second reinspection or premature inspection request
$19.00
Third reinspection or premature inspection request
38.00
Fourth reinspection or premature inspection request
63.00
 
      3.   Payment Of Fees: All fees are to be paid before a permit is issued. All fees for any classification hereinabove set forth shall be doubled if work is started without a permit unless prior arrangements have been made with the village inspections department. (Ord. 2005-1249, 11-15-2005)
   C.   Commercial Fees:
      1.   Electrical Fees:
   Service
Fee
   Service
Fee
Commercial electrical permit
$10.00
Commercial inspections:
Up to $2,001.00
41.00
Every additional $1,000.00 or part thereof
8.00
Semiannual inspection
38.00
Temporary pole service
23.00
Wiring for signs
20.00
First $1,000.00
20.00
Each addition $1,000.00 to $20,000.00
6.00
Each $1,000.00 over $20,000.00
3.00
 
(Ord. 2005-1249, 11-15-2005; amd. 2016 Code)
      2.   Reinspection Fees: Each reinspection for noncompliance to the building/electrical code or premature inspection request:
 
First reinspection or premature inspection request
Free
Second reinspection or premature inspection request
$19.00
Third reinspection or premature inspection request
38.00
Fourth reinspection or premature inspection request
63.00
 
      3.   Payment Of Fees: All fees are to be paid before permit is issued. All fees for any classification hereinabove set forth shall be doubled if work is started without a permit unless prior arrangements have been made with the village inspections department. (Ord. 2005-1249, 11-15-2005)