Spoil material resulting from clearing, grubbing and channel excavation shall be disposed in such a manner which will:
(A) Minimize overbank wash.
(B) Provide for the free flow of water between the channel and floodplain unless the valley routing and water surface profile are based on continuous dikes being installed.
(C) Not hinder the development of travelways for maintenance.
(D) Leave the right-of-way in the best condition feasible, consistent with the project purposes, for productive use by the owner.
(E) Be approved by the IDNR or U.S. Army Corps of Engineers (whichever is applicable) if deposited in the floodway.
(Ord. 1999-05, passed 6-8-99)