§ 152.16 RECORD DRAWINGS.
   (A)   Record drawings for all improvements are to be submitted to and accepted by the town, prior to final acceptance of the improvements. Record drawings shall be provided, as a minimum requirement, for the following:
      (1)   As-built volume and critical hydraulic control elevations for detention/retention basins.
      (2)   Compaction testing results from a certified geotechnical laboratory for embankments (Min. 95% of maximum dry density).
      (3)   Critical drainage grade breaks that affect design drainage flow patterns.
      (4)   Critical roadway elevations that control upstream ponding that affect minimum finished floor elevations established for the development.
   (B)   Certification of the record drawings shall be required as follows:
      (1)   If the record drawings show significant deviations between the plans and construction improvements, the town may require that a registered Professional Civil Engineer, licensed to practice in the State of Arizona, certify that "based on site visitations and to the best of their knowledge, belief, and opinion, the drainage facilities were constructed in accordance with the design intent of the accepted Final Drainage Report and Construction drawings."
      (2)   The town will compare the "certified record drawing" information with the construction drawings. A "certified record drawing" will be accepted only if: 1) the "record drawing" information demonstrates that the construction is in compliance with the design intent; and 2) the "record drawings" are certified by a registered Professional Civil Engineer, licensed to practice in the State of Arizona.
(Res. 1637, passed 2-28-02; Am. Res. 2871, passed 9-17-15; Am. Ord. 872, passed 9-17-15)