(A) No construction of improvements within the proposed subdivision shall begin until the final plat has been approved by the City Council.
(B) All public improvements proposed to be made under the provisions herein shall be inspected during the course of construction by the City Engineer or a duly designated deputy.
(C) During the course of construction of the improvements, the subdivider shall be required to notify the City Engineer 24 hours before each of the following operations in order that the Engineer or a duly designated deputy may make required inspections.
(1) Before base material is deposited in place for inspection of all street sub-grades.
(2) Before bituminous topping is placed on the base material, for inspection of the base construction.
(3) Before any back-filling operations whatsoever following the installation of water, sanitary or storm sewers or any other underground improvement.
(4) The subdivider shall pay the cost of all inspections. The fee shall be established by the city based on current rates and standard engineering practice.
(D) Any trenches, excavations or underground improvements shall be backfilled with screened aggregates of such character as to prevent sinking and undermining of surface improvements such as streets, curbs and sidewalks.
(E) All service boxes and buffalo boxes shall be located in the parkway and with due regard for the location of surface improvements such as sidewalks.
(Ord. 88-30, passed 8-8-88) Penalty, see § 151.999