§ 52.062 PERMIT DECISIONS.
   The Superintendent will evaluate the data furnished by the industrial user and may require additional information. Within 30 days of receipt of a complete wastewater discharge permit application, the Superintendent will determine whether or not to issue a wastewater discharge permit. If no determination is made within this time period, the application will be deemed denied. The Superintendent may deny any application for a wastewater discharge permit.
(Ord. 99-26, passed 9-13-99)