SUBDIVISION REVIEW PROCEDURE
PPC - Pawnee Planning Commission
Number Of Prints | Reviewed By | Payment | Approval Valid For |
Number Of Prints | Reviewed By | Payment | Approval Valid For | |
Location map minor subdivision | 12 | PPC | None | 1 year |
Location and sketch maps | 12 | PPC Village Board | None | 1 year |
Preliminary plan | 10 | PPC | $100.00 | 3 years |
Construction plans | 4 | Village Engineer | None | As long as preliminary current |
Final plat | 10 | PPC Village Board | $100.00 plus $5.00/lot | 2 years |
Preliminary plan reaffirmation | 10 | PPC | None | 3 years renewable 1 time |
Minor subdivision | 12 | PPC Village Board | $100.00 | 2 years |
Large scale development | 10 | PPC | Residential large scale development: $100.00 plus $3.00/unit or 1,000 sq. ft. of non-residential use Commercial or industrial large scale development: $500.00 plus actual cost to Village of plan review by engineers or other technical consultants | |
All plans shall be filed 2 weeks before the scheduled monthly Pawnee Plan Commission meeting with the Pawnee Village Clerk.
Exception: Construction plans - See subsection 10-4-3B of this title.
Note: Pawnee Plan Commission review must be completed in 2 consecutive, regularly scheduled meetings.
(Ord. 91-14, 9-23-1991; amd. Ord. 17-14, 8-14-2017)