§ 157.192 SITE PLAN APPROVAL.
   (A)   No zoning certificate or building permit shall be issued until a site plan has been approved for the development. A site plan shall not be required if an adequate site plan is already on file, there is no change in the parking requirements, or there is no increase in impervious surface area.
    (B)   Additions to existing buildings that exceed 10% of the gross floor area of the building or require an additional five or more parking spaces shall be approved by the Zoning Administrator upon recommendation of the Technical Review Committee.
   (C)   Site plans that require approval from the Technical Review Committee, must be submitted at least 21 days prior to the regular Technical Review Committee meeting.
   (D)   If a site plan is granted conditional approval by the Technical Review Committee, the applicant shall revise and resubmit the site plan. The Zoning Administrator shall review the revised site plan and, if it meets all the approval conditions and is otherwise substantially unaltered, shall signify on the plan the approval. If the site plan is not revised within 60 days to meet the approval conditions, or the applicant notifies the Zoning Administrator that he is unwilling to revise the site plan, it shall be deemed denied.
   (E)   Copies of all required state permits must be submitted to the Zoning Administrator prior to the approval of a site plan.
(Ord. passed 6-21-2021)