1032.06 CONSTRUCTION.
   Collocations for which permits are approved shall be completed within one hundred eighty (180) days of issuance of the permit, unless the Village agrees to extend the period or a delay is caused by make-ready work for a Village utility pole or by the lack of commercial power or backhaul availability at the site, provided the applicant has made a timely request within sixty (60) days after the issuance of the permit for commercial power or backhaul services, and the additional time to complete installation does not exceed three hundred sixty (360) days after issuance of the permit. Permits that are not completed within applicable timelines shall be void absent an extension granted in writing by the Village.
(Ord. 2018-25. Passed 8-13-18.)