§ 153.120 SUMMARY OF PROCEDURE.
   A generalized summary of the steps for consideration and approval of Planned Residential Developments and subdivision plans relating thereto is as follows:
   (A)   Preapplication conference or conferences are held with the plan commission and the planning and zoning committee of city council in order to obtain information and guidance in preparing the development application.
   (B)   The development application (conceptual and schematic), with plans and statements, is submitted to the plan commission and the planning and zoning committee of city council. A public hearing is held.
   (C)   The development plan is approved. Applicant is authorized to proceed with the preparation of the final subdivision application.
   (D)   The final subdivision application is filed with the city clerk. The plan commission shall recommend to the city council to approve, modify, and approve or disapprove the application within 60 days after the final subdivision application is filed.
   (E)   Applicant is notified of city council action by the city clerk. Approved subdivision plans are recorded as required herein and by statute.
   (F)   Applicant shall commence construction within 6 months, for an approved subdivision; and one year for an approved development, following recordation of approved plans. Upon his failure to do so, the development and approvals are voidable.
(Ord. O-17-70, passed 7-7-70; amend. Ord. O-23-73, passed 4-24-73)