§ 150.147 NEW HOMES, PATIO HOMES, TOWNHOUSES, CONDOS, COMMERCIAL CONSTRUCTION, HOME ADDITIONS AND RENOVATIONS.
   (A)   Foundation inspection. This inspection verifies the location of the structure with respect to building lines.
   (B)   Slab inspection. This inspection must be completed prior to the placement of concrete within the foundation forms. Verification of steel placement, elevation, and slab thickness will occur at this inspection.
   (C)   Cover-up inspection. This inspection is completed when all electrical, plumbing, and air conditioning rough-in is complete and prior to the placement of insulation or dry wall.
   (D)   Utility inspection. This inspection must be done prior to the connection of sewer and water connections.
   (E)   Driveway inspection. This inspection must be completed prior to placement of concrete or macadam in the driveway. All drainage culverts and steel reinforcement must be complete prior to this inspection.
   (F)   Final inspection. This inspection will be completed when the structure is ready for occupancy. If the structure passes this inspection, a Certificate of Occupancy will be issued.
(Ord. 2015-3, passed 5-7-2015)