(A) Commencement of construction prior to approval of plat. No construction of any kind shall be permitted prior to final subdivision approval by the City Council.
(B) Construction authorization. Prior to beginning any construction of the proposed subdivision, the applicant must have a preconstruction meeting with the Public Works Department. Authorization from the City Engineer in the form of a construction permit must also be obtained before any construction may begin.
(C) Clearing. Prior to commencement of clearing and/or land alteration activities, the applicant must receive the required Site Work Permit from the Land Development Division.
(Ord. 96-05, passed 2-15-96; Am. Ord. 2016-32, passed 5-19-16)