The applicant shall comply with the following requirements in order to begin construction on the public improvements pursuant to the approved improvement plan.
(a) The following items shall be approved prior to the commencement of construction:
(1) The improvement plans for the subdivision.
(2) The construction schedule, showing the starting and completion dates for each phase of the construction work, and a date for the completion of the entire subdivision.
(3) Any bonds required for the project shall be filed with the City.
(b) The contractor shall have all necessary permits required for the project prior to the start of construction.
(c) The applicant, the design engineer, the contractor, the City Engineer, the Administrator, and any other officials as may be required, shall attend a preconstruction meeting prior to the commencement of any project. At this time, the project will be discussed in regard to the procedure, construction methods, plans, materials, inspections, stormwater management, erosion control, and any other improvements as applicable.
(d) For phased development, each phase shall be considered as an independent unit and as such shall comply with the provisions of this Code and all other applicable regulations.
(Ord. 16-19. Passed 9-16-19.)