7-3-5: AS BUILT DRAWINGS:
A right-of-way user shall, within sixty (60) days of making an installation pf facilities in the city right-of-way, furnish the city with one (1) complete set of as built drawings, in an electronic format compatible with the city's mapping system, if required, drawn to scale and certified by the contact person for the right-of-way user as accurately depicting the location of the facilities installed pursuant to the permit. When the city has issued a single installation permit document relative to multiple installations linked in a single project, the as built drawing pertaining to those installations are not required as aforesaid until sixty (60) days after completion of all installations to be done for the project. (Ord. 2019-01, 5-14-2019)