§ 53.090 INSPECTION SCHEDULE AND REPORTS.
   (A)   The developer shall notify the engineer responsible for inspections at least 48 hours before commencing any work in conjunction with the stormwater management plan and upon completion of the project when a final inspection will be conducted.
   (B)   The developer shall retain a professional engineer licensed in the state to conduct inspections. Written inspection reports shall be made of the periodic inspections necessary during construction of stormwater management systems to ensure compliance with the approved plans.
   (C)   Written inspection reports shall be provided to the developer and Town Planning and Zoning Commission, its agent(s) or the Town Engineer and shall include:
      (1)   The date and location of the inspection;
      (2)   Whether construction was in compliance with the approved stormwater management plan;
      (3)   Any variations from the approved construction specifications; and
      (4)   Any violations that exist.
   (D)   The owner/developer and on-site personnel shall be notified in writing when violations are observed. Written notification shall describe the nature of the violation and the required corrective action.
   (E)   No work shall proceed until the Town Planning and Zoning Commission, its agent(s) or the Town Engineer approves the work previously completed. The inspector shall provide the developer and the Town Planning and Zoning Commission, its agent(s) or the Town Engineer with the results of the inspection reports as soon as possible after completion of each required inspection.
(Ord. passed 7-14-2008)