(A) If the work described in any building permit has not begun within 120 days from the date of issuance, the building permit shall expire. It shall be cancelled by the Administrative Officer/Building Inspector with written notice being given to the parties affected.
(B) If the work described in a building permit has not been substantially completed within two years of the date of issuance of the permit, the building permit shall expire and be cancelled by the Administrative Officer/Building Inspector, again with written notice given to the party affected, together with notice that further work as described in the cancelled permit shall not proceed unless and until a new building permit has been issued as provided in this chapter.
(Ord. 14-1986, passed 12-1-86)