The minimum bonding amounts are as follows:
Utility annual permit bond | $25,000 |
Underground linear construction, grading, trenching, or excavation parallel to the road | $10,000 per mile or fraction of a mile (maximum $15,000) |
Open road cut (paved) | $15,000 per location |
Open road cut (gravel) | $0 per location |
Bores or pushes under roadway | $5,000 per bore |
Placement/removal of poles/overhead lines | $5,000 per mile or fraction of a mile (maximum $15,000) |
Tap pit (including a directly associated push or bore) | $5,000 per pit |
Equipment crossing subdivision curbs and sidewalk, no excavation | $2,000 per crossing |
(Ord. 2020-0056, passed 11-2-2020)