(A) When all work is completed and as-built plans are approved by the town utility personnel, the developer/owner shall be notified that the request can be made for town acceptance of utilities.
(B) The developer/owner shall submit to the town utility personnel the following information:
(1) Engineer's as-built certification that the work was completed substantially in accordance with the approved plans.
(2) Three year letter of credit or maintenance bond for 10% of the amount of work completed and requested for acceptance.
(3) Request for town acceptance of the completed public improvements.
(C) Upon acceptance of the public improvements by the Town Council, the developer/owner, lot owner or contractor may apply for sewer and water permits.
(D) The town shall not accept utilities until all fees have been paid and all required information has been submitted, reviewed, and accepted.
(Ord. 2019-1001, passed 10-1-2019)