8-2-37: AS-BUILT DRAWINGS AND ENGINEER'S CERTIFICATION:
   A.   As-Built Or Record Drawings: As-built or record drawings of sewer line plans shall be prepared by a professional engineer and the "corrected" original drawing or a duplicate mylar copy of the "corrected" original drawing(s) shall be provided to the City.
   B.   Certification Required: As-built plans shall include a certification thereon signed by the registered professional engineer in charge of the work that the as-built drawings are true and correct and that he/she (the registered professional engineer) has inspected the construction of the sewer line installation and that the materials and installation of same were all done in conformity with the standard specifications for the construction of sanitary sewers and storm sewers. (Ord. 655, 9-27-1994)