§ 150.167 CURING.
   Driveways must be cured by one of the following methods and must remain in place for not less than six days:
   (A)   Apply specified curing compound with brush, roller, or spray at the rate of one gallon for every 250 square feet of surface.
   (B)   Place burlap on the finished surface, saturate with water, and cover with an impermeable covering.
   (C)   Place polyethylene sheeting as soon as the concrete has hardened sufficiently to prevent marring of the surface. Wet the surface of the concrete immediately before the sheeting is placed. The edges of the sheeting shall be weighted securely with a continuous windrow of earth or any other means satisfactory to the village to provide an air-tight cover.
(Ord. 77-23, passed 11-23-77) Penalty, see § 150.999