(a) The Building Department shall adopt an administrative, nondiscretionary review process to expedite the approval of electric vehicle charging stations applications within 30 days of the adoption of this chapter.
(b) An application for electric vehicle charging stations that meets the requirements of the checklist and required permitting documentation of all requirements shall be deemed complete, and the Building Department shall issue a building permit or other non-discretionary permit at expedited rate.
(c) Review of the application shall be limited to the Building Department’s review of whether the applicant meets local, state and federal health and safety requirements.
(d) If an application for electric vehicle charging station is deemed incomplete, a written correction notice detailing all deficiencies in the application and any additional information or documentation required to be eligible for expedited permitting shall be provided to the applicant for resubmission.
(e) Inspections shall be required and performed by the Building Department for electric vehicle charging stations.
(f) The inspection shall be done in an efficient inspection process, in a timely manner, and should include consolidated inspections; inspection measures taken should be consistent with safety requirements to ensure that the electric vehicle charging stations are properly installed.
(g) If electric vehicle charging station fails inspection, a subsequent inspection is authorized but need not conform to the requirements of this chapter.
(§ 2, Ord. 3061, eff. December 1, 2016)