Sec. 7-5.09. Extension of time.
   When the progress toward the completion of any district is impeded by any circumstance beyond the control of the City, any utility, or any owner, then each and every day such delaying circumstance continues to exist shall not be counted as a project work day. Such nonchargeable days shall constitute an automatic extension of the project time period.
   Specific extensions of time may be requested for good cause submitted in writing to the Council by any agency, utility, or owner participating in any district.
(§ 9, Ord. 1687, eff. June 20, 1968)