§ 50.101 PERMIT EXTENSIONS.
   (A)   A CDDL of less than one acre shall not be granted a permit extension.
   (B)   A CDDL of greater than one acre may apply for a permit extension under the following conditions.
      (1)   Application for a permit extension must be made 180 days prior to the expiration of the existing permit, unless permission is granted for a later date by the Solid Waste Coordinator.
      (2)   Applications for renewal must follow the application requirements outlined in § 50.096(A), (B)(1), (C) and (D).
   (C)   The Solid Waste Coordinator shall consider whether all conditions of the original permit and modifications of permit conditions were met. The Solid Waste Coordinator may request updated information necessary for reevaluating the permit’s suitability for reissuance and impose additional or modified permit conditions when deemed appropriate.
   (D)   Permit renewals shall be issued for an additional ten-year period.
(Ord. KOC 97-830-53, passed 9-2-1997)