1164.09 PERFORMANCE STANDARDS.
   (a)    Prior to the start of grading and within seven days from the start of grubbing the applicant must implement the erosion and sedimentation controls.
   (b)    Erosion and sedimentation controls shall meet these minimum performance standards:
      (1)    During active construction:  
         A.   Non-structural preservation measures. The applicant must make use of practices that preserve the existing natural condition to the maximum extent practicable as determined by the Village Engineer. Such practices may include preserving riparian areas, preserving existing vegetation and vegetative buffer strips, phasing of construction operations in order to minimize the amount of disturbed land at any one time, and designation of tree preservation areas or other protective clearing or grubbing practices.
         B.   Erosion control practices. The applicant must make use oferosion controls that are capable of providing cover over seventy percent (70%) of disturbed soils.
         C.   Runoff control practices. The applicant must make use of measures that control the flow of runoff from disturbed areas so as to prevent erosion. Such practices may include rock check dams, pipe slope drains, diversions to direct flow away from exposed soils and protective grading practices. These practices shall divert runoff away from disturbed areas and steep slopes where practicable.
         D.   Sediment control practices. The applicant must install structural practices that shall store runoff, allowing sediments to settle and/or divert flows away from exposed soils or otherwise limit runoff from exposed areas. Structural practices shall be used to control erosion and trap sediment from a site remaining disturbed for more than 7 days. Such practices may include, among others: sediment settling ponds, silt fences, storm    drain inlet protection, and earth diversion dikes or channels which direct runoff to a sediment settling pond. All sediment control practices must be capable of ponding or filtering runoff in order to be considered functional. Earth diversion dikes or channels alone are not considered a sediment control practice unless used in conjunction with a sediment settling pond.
         E.   Non-sediment pollutant controls: No solid or liquid waste, including building materials and concrete wash out water shall be discharged in storm water runoff. The applicant must implement site best management practices to prevent toxic materials, hazardous materials, or other debris from entering water resources or wetlands.
         F.   Trench and ground water control. There shall be no sediment laden or turbid discharges to water resources or wetlands resulting from dewatering activities. If trench or ground water contains sediment, it must pass through a sediment-settling pond or other equally effective sediment control device, prior to being discharged from the construction site. Alternatively, sediment may be removed by settling in place or by dewatering into a sump pit, filter bag or comparable practice. Ground water dewatering which does not contain sediment or other pollutants is not required to be treated prior to discharge. However, care must be taken when discharging ground water to ensure that it does not become pollutant-laden by traversing over disturbed soils or other pollutant sources.
      (2)   Maintenance. All control practices shall be maintained and repaired as needed to ensure continued performance of their intended function until final stabilization. All sediment control practices must be maintained in a functional condition until all up slope areas they control reach final stabilization. When inspections reveal the need for repair, replacement, or installation of erosion and sediment control BMPs, the following procedures shall be followed:
         A.   When practices require repair or maintenance. If an inspection reveals that a control practice is in need of repair or maintenance, with the exception of a sediment-settling pond, it must be repaired or maintained within three (3) days of the inspection. Sediment settling ponds must be repaired or maintained within ten (10) days of the inspection.   
         B.   When practices fail to provide their intended function. If an inspection reveals that a control practice fails to perform its intended function as detailed in the ESCP and that another, more appropriate control practice is required, the ESCP must be amended and the new control practice must be installed within ten (10) days of the inspection.
         C.   When practices depicted on the ESCP are not installed. If an inspection reveals that a control practice has not been implemented in accordance with the schedule, the control practice must be implemented within ten (10) days from the date of the inspection. If the internal inspection reveals that the planned control practice is not needed, the record must contain a statement of explanation as to why the control practice is not needed.
      (3)   Final stabilization defined. The site reaches final stabilization when all    soil disturbing activities are complete and a uniform perennial vegetative    cover with a density of 70 percent coverage for the area has been established on all unpaved areas and areas not covered by permanent structures. In addition, all temporary erosion and sediment control practices have been removed and disposed of in an acceptable manner.
   (c)   Post construction water quality practices.  
       (1)   Non-structural water quality practices: Non- structural post construction best management practices include preservation, planning, or procedures that direct development away from water resources or limit creation of impervious surfaces. Practices such as conservation easements, riparian and wetland setbacks, and conservation subdivision design are all non-structural controls.
         A.   All non-structural water quality practices must be protected from disturbance throughout the construction phase of the project.
         B.   All non-structural water quality practices must be protected in perpetuity through the use of appropriate legal tools. All easement or conservation areas must appear on the final plat or other legal document.
      (2)   Structural water quality practices: Structural post construction best management practices are permanent features constructed to provide treatment of storm water runoff either through storage, filtration, or infiltration. All structural water quality practices must be established prior to the completion of the project. Structural water quality practices should be made functional once the disturbed areas on site are stabilized. If detention/retention facilities were used for sediment control uring     development sediments must be removed prior to the basin being used for post construction storm water quality.
      (3)   Maintenance. The post construction water quality practice must be maintained in perpetuity by those parties identified in the ESCP or the Storm Water Management Maintenance Agreement.
         (Ord. 37-10. Passed 12-13-10.)