§ 152.11 INSPECTIONS.
   (A)   (1)   The City Engineer and the Director of Public Works shall make inspections as required in this section and shall either approve the portion of the work completed or shall notify the permittee wherein the same fails to comply with the site development plan.
      (2)   Where it is found by inspection that conditions are not substantially as stated or shown in the plan, they may stop further work until approval is obtained for a revised grading plan conforming to the existing conditions.
      (3)   Plans for grading work, bearing the stamp of approval of the City Engineer and the Director, shall be maintained at the site during progress of the grading.
      (4)   Until the final inspection is made, a sign issued by the city indicating that permission to grade has been granted by the city shall be prominently displayed on the front property line of the property involved so as to be visible from the street on which the property fronts.
   (B)   In order to obtain inspections in accordance with the following schedule, the permittee shall notify the City Engineer and the Director at least two full working days before the inspection is to be made:
      (1)   Rough grading. When all rough grading has been completed; and
      (2)   Final inspection. When all work, including the installation of all drainage and other structures and required planting, has been completed.
(2000 Code, § 15.44.110)