§ 53.066 AS-BUILT PLANS, COMPLETION CERTIFICATE AND FINAL INSPECTION.
   (A)   (1)   The developer shall be responsible for providing as-built plans of all SWM BMPs included in the approved SWM site plan.
      (2)   The as-built plans and an explanation of any discrepancies with the construction plans shall be submitted to the municipality.
   (B)   (1)   The as-built submission shall include a certification of completion signed a qualified person verifying that all permanent SWM BMPs have been constructed according to the approved plans and specifications.
      (2)   If any licensed qualified person contributed to the construction plans, then a licensed qualified person must sign the completion certificate.
   (C)   After receipt of the completion certification by the municipality, the municipality may conduct a final inspection to verify compliance with, and accuracy of, the as-built plans.
   (D)   (1)   Once the as-built plans are approved by the municipality, digital copies of the as-built plans and executed certification of completion shall be provided to the municipality and their Engineer.
      (2)   This shall be in addition to the digital copies of the plan required by § 53.062(E).
(Ord. 2013-2, passed 10-7-2013)